Renovation
Better indoor climate and less noise at SDU in Sønderborg
SDU's buildings at Alsion in Sønderborg will be renovated to create better conditions for staff and students.
Purpose
The purpose is to address the challenges with acoustics and indoor climate that have been recurring issues in workplace assessments throughout the building's lifetime. These include the acoustics in the atriums, sound transmission between the atrium and offices, sound transmission between the U-rooms, as well as air quality and temperature, especially in the offices and teaching rooms.
The solutions
In the atriums (blocks B, D and F), acoustic/reverberation-regulating absorbent materials will be installed on various surfaces, both on walls and ceilings.
Acoustic sealing of the window bands between the atriums and the surrounding offices will be installed.
Noise transmission between the teaching rooms will be reduced.
Mechanical ventilation will be installed to replace natural ventilation (automatic opening of windows). In short, mechanical ventilation means ventilation units (placed on the roofs) that send filtered and tempered fresh air to the rooms through ducts above the ceilings, while extracting the used air at the same time, thereby ensuring continuous air exchange – without opening the windows.
An external solar film will be installed on the glass facades of east-facing offices (facing the water) to limit the sun's heat gain while still allowing as much daylight as possible. At present, there is no external sun screening on the east side.
All lighting in the affected rooms will be replaced with LED
The consequences
Scaffolding will be erected in the atriums to allow work on the facades and ceiling. For safety reasons, access and movement will therefore be limited during the periods when work is taking place.
No air ducts can be installed above the ceilings without dismantling them, and naturally the work cannot take place unless the rooms are cleared of furniture. An unavoidable consequence is therefore that all affected rooms must be emptied, which requires activities in the rooms to move to another location while the work is under way.
The ducts must run from the roof and down through the floor slabs to each floor, from where they will branch out to all affected rooms. This makes it necessary to clear entire blocks of activities and furniture. However, this does not apply to most laboratories, where only minimal work will take place. Ongoing research will continue here, as will access to the laboratories. In addition, floor 0 (the basement) is generally not included in the project.
A list of affected rooms will follow.
The construction site requires an area for material storage, parking and similar purposes. This area will be placed in the lower car park, which means that approximately one third of the car park will be used throughout the construction period.
A construction site of this scale, in the middle of a building that remains in operation, will cause unavoidable disruption such as noise and dust.
The timetable
To accommodate both the possible progress of the work, the building's operation, and a limit on the need for temporary relocation space, the work will be divided into 3 phases:
- 1. Renovation of blocks E and F will take place in the autumn semester of 2027
- 2. Renovation of blocks C and D will take place in the spring semester of 2028
- 3. Renovation of blocks A and B will take place in the autumn semester of 2028
A more detailed timetable, especially for moving in/out and similar matters, will follow as soon as agreements on temporary relocation rooms, removal companies and similar arrangements are in place.
The timetable will of course take particular account of the examination periods.