Most noise in week 42
In week 42, the project will carry out as much of the noisy work as possible in order to shorten the overall period of noise disruption.The work will take place in the unfinished space on the lower ground floor beneath U300 and U301. Openings will also be cut into the façade facing the light rail. In week 42, cutting work will take place every day from 7.00 to 16.00. Employees are therefore encouraged to:
- work from home during week 42 if their tasks allow it
- schedule experiments and other laboratory work affected by high levels of noise and vibration outside week 42, if possible.
From week 43 up to and including week 51, cutting work is expected to continue from 18.00 to 24.00. According to the current schedule, the work will be completed on 20 December 2026.
Check operational status updates
The entire period of cutting work in weeks 42–51 will be added later this week to SDU’s operational status page and to the operational status page for Dyrestalden/BML.
If you have any questions about the work, please contact project manager Ditte Marie Salling on 6550 9679.
This information has been sent on behalf of Ole Skøtt, senior consultant and head of the simulation laboratory.